Amending Subcode "A" (The Philadelphia Administrative Code) of Title 4 of The Philadelphia Code, entitled "The Philadelphia Building Construction and Occupancy Code," by providing for the manner of payment of electrical permit fees for the installation of solar electric (also known as photovoltaic) systems.

AI summary

This enacted law changes how Philadelphia calculates electrical permit fees for projects that install solar electric, or photovoltaic, systems. When calculating the fee, the city does not include the cost of the system’s solar arrays or inverters, affecting permit applicants for these installations.

File details

Status
ENACTED
Introduced
June 23, 2011
Sponsors
JFJames F. Kenney
View official record ↗

Full text

THE COUNCIL OF THE CITY OF PHILADELPHIA HEREBY ORDAINS:

SECTION 1. Title 4 of The Philadelphia Code is amended to read as follows:

TITLE 4. THE PHILADELPHIA BUILDING CONSTRUCTION

AND OCCUPANCY CODE.

* * *

CHAPTER 4-200. TEXT OF SUBCODES

SUBCODE “A” (THE PHILADELPHIA ADMINISTRATIVE CODE)

* * *

CHAPTER 9 FEES

* * *

SECTION A-903 ELECTRICAL CODE FEES

* * *

A-903.2 Electrical permit fees: The permit fee for electrical work shall be $25.00 for each $1,000.00 or fraction thereof of estimated electrical construction costs. The minimum fee shall be $25.00. The maximum fee shall be $7,500.00.

Except as provided in Section A-903.2.1,

[The]

the

construction costs shall be determined by inclusion of the following:

1. All electrical equipment, conductors, conduit, etc.,

2. All material,

3. All labor,

4. Overhead and profit.

A-903.2.1 Calculation of construction costs for solar electric (also known as photovoltaic) systems.

A-903.2.1.1 Solar electric system or photovoltaic system defined: For the purposes of this subsection, the terms “solar electric system” and “photovoltaic system” shall each mean the total components and subsystems that, in combination, convert solar energy into electrical energy suitable for connection to a utilization load.

A-903.2.1.2 For the purpose of calculating the electrical permit fee, the electrical construction costs for any project that includes installation of a solar electric or photovoltaic system shall not include the cost of any arrays or inverters used in the installation of such systems.

[A-903.2.1]

A-903.2.2

Pre-paid permits: * * *

* * *

______________________________

Explanation:

[Brackets] indicate matter deleted.

Italics

indicate new matter added.

End

File history

Sometimes city council's record keeping is not complete. This timeline reflects the information on the council's legistar website.
  1. Council actionMAYOR

    Signed

  2. Council actionCITY COUNCIL

    Ordered placed on next week`s second reading calendar

    Council actionCITY COUNCIL

    Suspend the rules of the council

    Pass
    Council actionCITY COUNCIL

    Ordered placed on this day`s first reading calendar

  3. Council actionCommittee on the Environment

    Reported favorably, rule suspension requested

    Council actionCommittee on the Environment

    Amended

    Council actionCommittee on the Environment

    Hearing held

    Council actionCommittee on the Environment

    Hearing notices sent

  4. Council actionCITY COUNCIL

    Introduced and Referred

    Pass